Indices
Highlights of the month
One public headline number per model, with the document it came from and the date. The methodology is on the model page; class detail and history are Pro and Institutional. The vermilion figure is the most recent reading.
12 of 90Cells scored Yes across 18 OEMs and five disclosure criteria
OEM Disclosure Scorecard
Yes cells across 18 OEMs and five criteria (lead-time guide, list prices, backlog in dollars, capacity in units, delivery performance). Backlog in dollars: 10 of 18 OEMs. No OEM publishes delivery performance.
50 weeksLV switchgear
Lead-Time Monitor
Low-voltage switchgear (LVDO), made to order. Source: Schneider Electric Lead Times Guide, September 2026 edition, published 2 September 2026. Eleven classes tracked; class detail is Pro.
$69 /kVAPad-mount 3-phase 225 to 500 kVA
Public Bid-Tab Price Book
Median public award price, pad-mount 3-phase 225 to 500 kVA, n=60, 11 buyers, 11 states, awards 2024-02-06 to 2026-08-24. 2,712 award lines, 51 published bands. Bands free; rows Pro.
2033realistic energization year for a new 50 MW load in Northern Virginia
Large-Load Cost Table
Realistic energization year for a new 50 MW load, Dominion Energy Virginia. Source: JLL Global Data Center Outlook 2026, p.18 (about seven years to power in Northern Virginia); Dominion queue 70 GW against a 24.6 GW peak, February 2026. Table as of 21 August 2026.
3.0 xPowell Industries book-to-bill
Book-to-Bill League Table
Powell Industries, quarter ended June 30 2026, orders $934M on revenue $311.7M, reported ratio. Source: Powell Q3 FY2026 earnings release, 8-K Ex. 99.1, filed August 3 2026. Eighteen OEMs in the table; full table is Pro.
$9.8M per MWall-in datacenter build cost
Datacenter MEP Cost Table
All-in build cost, Phoenix and Columbus. Source: Turner & Townsend, Data Centre Construction Cost Index 2025, cost per watt by market; compiled 13 March 2026 for Chillers Are the 60-Week Problem. Component lines are Pro.
How a headline is chosen
Each model page states the rule for its headline: the longest OEM-published lead time for the Lead-Time Monitor, the longest realistic energization year among fifteen markets for the Large-Load Cost Table, the highest reported book-to-bill in the quarter for the Book-to-Bill League Table, the Turner & Townsend build cost for the lowest-cost US Tier 1 market for the MEP Cost Table, and a count of filings for the OEM Disclosure Scorecard. A model with no number that meets its rule prints none: the Public Bid-Tab Price Book reads "Collecting" until 300 awards are normalized.