Datacenter MEP Cost Table
Capex per MW by component on the Turner & Townsend and JLL baselines, air-cooled and liquid-cooled, with each line's lead time from the Lead-Time Monitor and the carrying cost of delay.
$9.8M per MWall-in datacenter build cost, Phoenix and Columbus, Turner & Townsend Data Centre Construction Cost Index 2025. Public headline as of March 13, 2026.
- $9.8M per MW
- Build cost, Phoenix and Columbus ($9.8 per W); Atlanta $9.9, Silicon Valley $13.3, Tokyo $15.2. Turner & Townsend DCCI 2025
- 54%
- Electrical including equipment as a share of an air-cooled US build; 48% liquid-cooled. Turner & Townsend DCCI 2025
- 22% to 33%
- Mechanical including equipment, air-cooled to liquid-cooled. At $9.8 per W that is $2.2M to $3.2M per MW
- 7 to 10%
- Cost premium for a liquid-cooled US build over air-cooled, Turner & Townsend DCCI 2025
What it covers
Capex per MW from utility fence to rack, by component: MV service and substation, transformers, MV and LV switchgear, UPS or BESS, gensets, busway and PDUs, chillers, CDUs, piping and controls. Air-cooled and liquid-cooled baselines on the Turner & Townsend cost allocation and the JLL and CBRE $/W by market, each line carrying its published lead time from the Lead-Time Monitor and a carrying-cost-of-delay figure at the 10-year Treasury rate.
- Cadence
- Quarterly, after the Lead-Time Monitor's quarter-end edition; baselines refreshed when Turner & Townsend and JLL publish
- Compiled from
- Turner & Townsend Data Centre Construction Cost Index 2025 (cost per W by market, US cost allocation by category); JLL Global Data Center Outlook 2026 and CBRE North America reports (as reported by the trade press where paywalled); vendor filings for equipment share; Open Factory Lead-Time Monitor; FRED GS10 for the carrying-cost rate
- Delivered as
- Excel workbook, Web dashboard
- Updates
- Quarterly updates, one year included
- Onboarding
- Onboarding call
- Support
- Ad hoc analyst calls
- Tier
- Pro; workbook Institutional
Who uses it and what it decides
- Datacenter developers and owner's repsA component-level budget per MW for a market, and which three lines drive the schedule.
- MEP engineers and EPCsWhether a design estimate sits inside the published range for its cooling type.
- Investors and lendersCapex per MW by cooling type and market for underwriting, with the source beside each line.
Methodology
What the headline is
$9.8 million per MW is the all-in construction cost for a datacenter in Phoenix or Columbus in Turner & Townsend’s Data Centre Construction Cost Index 2025, printed there as $9.8 per watt. The same index puts Atlanta at $9.9, Silicon Valley at $13.3 and Tokyo at $15.2, and allocates a US air-cooled build 54% to electrical including equipment, 22% to mechanical including equipment, 14% to core, shell and architectural and 10% to GC fees. A liquid-cooled build shifts to 48% electrical and 33% mechanical at a 7 to 10% premium. The allocation rows are in 06-mep-cost-shares.csv.
The headline is the Turner & Townsend figure for the lowest-cost US Tier 1 market and moves when the index is republished.
What it is compiled from
Version 0.1 is published baselines and arithmetic. No contributed quotes.
- Baselines. Turner & Townsend DCCI 2025 for $/W by market and the category allocation. JLL Global Data Center Outlook 2026 and CBRE North America reports for market context, cited “as reported by” the outlet where the report is paywalled.
- Component split. The electrical and mechanical shares are broken into lines using vendor disclosures where they exist (Vertiv’s 2025 annual report for thermal versus power mix, Morgan Stanley’s GB300 cooling BoM as reported by Tom’s Hardware, $49,860 per rack) and trade estimates marked as such (CDUs $500 to $800 per kW installed, Energy Solutions, verify).
- Lead times. Each line carries its class from the Lead-Time Monitor: LV switchgear 50 weeks (Schneider, September 2026), water-cooled chillers over 1,000 tons 50 to 70 weeks and CDUs 30 to 50 weeks (Origin Partners, May 2026), large power transformers above 160 weeks (Wood Mackenzie 2026, as reported by pv magazine).
- Carrying cost. FRED GS10, 4.80% on 8 September 2026.
Every line prints its source and whether it is a published figure, a derived split or a trade estimate.
What is free and what is paid
- Free: the headline, this page, and the cost-share chart in Chillers Are the 60-Week Problem.
- Pro: the component table per MW for air-cooled and liquid-cooled builds, by market, with lead times and carrying cost.
- Institutional: the workbook with the split arithmetic exposed, the dashboard, quarterly updates for a year, an onboarding call and ad hoc calls.
Articles built on it
Chillers Are the 60-Week Problem and The $60 Million Deposit: How Equipment Slots Became Datacenter Currency. Forward assumptions on density, 800 VDC and cooling type sit on the Datacenter Electrical Roadmap and the Cooling Roadmap.
Version history
- 0.1 (March 2026). Turner & Townsend 2025 index, JLL 2026 outlook, Lead-Time Monitor September 2026 edition for lead times.
What version 1 adds
Bid-tab awards for chillers, gensets and switchgear from the Public Bid-Tab Price Book replace the derived splits line by line as cells fill, and contributed MEP quotes from the Equipment Price Benchmark enter under the cell-size rules. Each replaced line will say which version replaced it.
Known gaps
The component split below the electrical and mechanical totals is derived, not published, and is marked derived. CDU and chiller unit prices are trade estimates until awards accumulate. Turner & Townsend’s index is annual; between editions the table ages and says so.
Questions
Is this a cost estimate for my site?
No. It is a table of published baselines with the arithmetic shown. A site estimate against your design is an advisory engagement.
Why Turner & Townsend and not an OEM price list?
No OEM publishes a $/MW price for switchgear, UPS or chillers at datacenter scale. The consultancies publish the only dated, market-level baselines. Transaction prices arrive through the Public Bid-Tab Price Book as awards accumulate.
What is the carrying cost of delay?
The interest on capex already spent while the longest-lead item is outstanding, at the 10-year Treasury rate on the date of the edition (4.80% on September 8 2026), per MW per month.
Articles built on this model

Modular Is Not Cheaper: A 50 MW Prefab Electrical Room, Line by Line
Austin Energy paid Crown Texas $725,183 for one prefabricated 16 by 60 foot control house in June 2023. The house was $489,270 of that. The truck was $12,500, the stairs shipped separately for $5,000, and the crew that unloaded and anchored it billed…

800 VDC Will Strand Your White-Space Frame Agreement
NVIDIA put a ship date on 800 VDC on August 11, 2026: the MGX power rack arrives in the second half of 2026. A 2 MW-per-row power center with an 800 VDC busway follows in 2027, and a DC power block that converts grid power in one step is the design for new…

Liquidated Damages at 0.5% a Week: Why Caps Sit at the Vendor's Margin
A week of delay on a 50 MW datacenter hall costs about $2.7 million. The liquidated damages clause in the transformer contract behind that hall pays back $74,000 for the same week, and stops paying after ten weeks. On a 2 MW plant the ratio is worse:…

The R-454B Summer: What the Refrigerant Switch Did to Chiller Prices
A 20 lb cylinder of R-454B cost $345 in 2021 and traded at $700 to $2,000 in July and August 2025. On May 26, 2026 EPA finalised a rule (91 FR 31284, effective July 27) that lets the last R-410A houses be installed and leaves every comfort-cooling chiller on…

OFCI vs Design-Build: How Hyperscalers Buy Chillers and Colo Developers Do Not
A water-cooled chiller over 1,000 tons quoted at 50 to 70 weeks in May 2026. The developer who lets the mechanical subcontractor buy it after the guaranteed maximum price pays about 15% more for a machine that arrives 20 weeks late. The route the…

Reading a Switchgear Quote: The Eleven Line Items That Hide the Schedule
Riverside Public Utilities paid $2,561,551.88 for one 15 kV metal-clad switchgear lineup in June 2024, and the unit was still in the factory eighteen months later. The board memo that approved the purchase put delivery in the first quarter of 2026; the next…

The $60 Million Deposit: How Equipment Slots Became Datacenter Currency
One GE Vernova 7HA.02 is 384 MW. At the ~$790/kW that BNP Paribas estimates GE Vernova is now getting for a heavy-duty turbine (July 2026), that one machine is ~$300 million of equipment, and the 20% reservation payment that holds a production slot for it is…

Behind the Meter, In Front of the Queue: 90 GW Announced, 2 GW Running
Datacenter developers have announced about 90 GW of behind-the-meter generation across 59 US projects, and about 2 GW of it runs, which is 2.2%. Another 1.2% is under construction, 36% holds an air permit, and 60% exists as a press release. The same month…

Five Majors Bought Their Way Into Liquid Cooling. Here Is the Price List
Ecolab agreed on March 20 to pay $4.75 billion for CoolIT Systems, 29 times the next twelve months' adjusted EBITDA on about $550 million of CDU and cold-plate sales. Eight days earlier Eaton had closed its $9.5 billion purchase of Boyd Thermal, agreed in…

Recips vs Turbines vs Fuel Cells for a 100 MW Bridge
A 100 MW bridge plant run for five years costs $96 per MWh on solid oxide fuel cells, $104 on gas reciprocating engines and $112 on aeroderivative gas turbines. That is at 85% utilization with gas delivered at $3.78/MMBtu, and the ranking holds at every gas…

Chillers Are the 60-Week Problem
A water-cooled chiller over 1,000 tons quotes at 50 to 70 weeks in the United States as of May 22, 2026. An air-cooled machine over 500 tons is 40 to 60 weeks and a coolant distribution unit 30 to 50. None of those is the longest line on a datacenter…

What 2,439 Public Change Orders Show About Electrical and Mechanical Contractors
The median electrical or mechanical contract in our set of 1,096 federal awards closed 1.8% above its award price. The dollars closed 9.5% above it. That gap between the typical contract and the typical dollar is the whole story of change orders: most jobs…

1872, Foundational Industries and Hadrian: Three Blueprints for the Autonomous American Factory
Three companies are building the autonomous American factory from three directions, and between July 2025 and August 2026 they raised $1.41 billion to do it. 1872 took $15 million to run robotic steel fabrication out of a 1903 building in Cincinnati.…

Who Bought the EV Plants' Machines
Companies cancelled, closed or downsized $34.8 billion of US clean-energy projects in 2025, 61 of them, against $12.3 billion of new announcements, and EV and battery plants were more than $21 billion each of the loss. That is E2's count, and it is the wrong…

When a Megapack Beats a Static UPS
A 24 MW, 48 MWh block of twelve Tesla Megapack 2 XL units costs about $14.4 million installed at January 2026 prices, $10.1 million after the 30% storage credit, and the N+1 static UPS it would sit next to in a 20 MW hall costs about $17.5 million. A grid…

The OEM Disclosure Scorecard: Who Tells Buyers Anything
Twelve of ninety cells. That is how many times one of the eighteen largest electrical, power and cooling OEMs selling into US factories and datacenters publishes, in a form a buyer can open without an account, one of five things a buyer needs: a dated lead…

What Hyperscaler Nuclear PPAs Tell a Factory Negotiating a 15-Year Contract
Microsoft is paying about $112 per MWh for 835 MW from a reactor that shut in 2019, and it signed for 20 years. That is the Jefferies estimate for the Crane restart, published five days after the deal, and Bloomberg Intelligence put it at $100 (Bloomberg,…

Why Your Switchgear Costs 50% More Than in 2021
The BLS producer price index for switchgear and switchboard manufacturing stood at 394.8 in July 2026, 78% above January 2021. Wood Mackenzie's survey puts medium-voltage switchgear at +50% since 2021 and circuit breakers at +47%, as reported by POWER…

The 30% Fuel-Cell ITC Is the Last Federal Subsidy for On-Site Power
On July 4, 2025, Congress cut the federal investment credit for every kind of on-site generation a factory can buy except one. Wind and solar lose it unless construction starts by July 4, 2026. Gas engines and turbines never had it. Natural-gas fuel cells,…

Vertiv Stopped Reporting Its Backlog. Here Is Our Estimate
Vertiv's order backlog was $15.0 billion on December 31, 2025, up 109% in a year, on a fourth-quarter book-to-bill of ~2.9x. That was the last time the company printed the number. The April 22 and July 29, 2026 releases have no backlog, no orders and no…

One Steel Mill Gates Every US Transformer
Every pound of domestic grain-oriented electrical steel in a US transformer core is melted in one electric arc furnace in Butler, Pennsylvania, at a plant with 0.3 million net tons of configured raw steel capacity and a maximum finished coil width of 920 mm.…

Tariff Bill of Materials: What Sections 232 and 301 Add to a UPS, a Lineup, a Genset and a Megapack
A 1 MW UPS assembled in the United States from the parts a US OEM actually buys carries about 17 points of federal duty in its ex-works price. The same UPS imported finished from China carries 55. The "50% copper tariff" that every quote now cites is 3.8 of…

Introducing the Public Bid-Tab Price Book
On March 19, 2024, Fayetteville Public Works Commission in North Carolina opened twelve bids for four 2,500 kVA three-phase pad-mount transformers and the unit prices ran from $64,285 to $219,000, a 3.4x spread on one stock number, with quoted lead times…

Cummins and Caterpillar Are Sold Out Through 2028
Cummins is taking generator orders "well into 2028" and Caterpillar closed June 2026 with $72.1 billion of firm backlog, $29.2 billion of it not shipping inside twelve months. Those two sentences come from Cummins' fourth-quarter call on February 5, 2026 and…

The 171-Day Capex Lead Time: ISM's Most Ignored Table
The average manufacturing buyer now commits to capital equipment 171 days ahead of need, and 27% of them commit more than a year out. Those two numbers sit in the Buying Policy table on the last page of the ISM Manufacturing Report On Business, below the…

Book-to-Bill League Table, Q2 2026: Every Electrical OEM
Powell Industries booked $934 million of switchgear orders in the quarter to June 30 2026 and shipped $312 million, a book-to-bill of 3.0. That is the top of the table. The bottom of the table is Eaton at 1.2, and Eaton is the only one of eight…

Introducing the Open Factory Lead-Time Monitor
A low-voltage switchgear section ordered from Schneider Electric today is quoted at 50 weeks from release to manufacturing, per the September 2026 edition of Schneider's Lead Times Guide, published September 2. That number is one of exactly four equipment…