Large-Load Interconnection Cost
MW and market to study fees, security deposit, minimum-bill exposure and realistic energization year, from the Large-Load Cost Table.
Method
Every cell is read from the Large-Load Cost Table row for the market, compiled for What 50 MW costs in 15 markets with status as of 2026-08-21. Minimum-bill exposure is the sum over the contract term of the published minimum billing demand (85% of contract capacity for Dominion, 80% for Xcel and SRP, 75% for Duke, AEP Ohio’s 15,000 kW plus 85% above 25,000 kW), applied to the ramped contract capacity where a ramp is published, and dollarized at the demand charge you enter. Security scales with MW only where the source gives a per-MW figure; implied averages (ComEd, CenterPoint) are labelled implied. Cells the sources do not publish render as “not published”; nothing is estimated.
Every input is mirrored to the URL so a scenario can be shared as a link.
Default assumptions come from the Large-Load Cost Table. Pro subscribers can save inputs. Institutional seats get the underlying series.
Articles that use this calculator

What 50 MW Costs in 15 US Markets
A 50 MW connection requested in Northern Virginia this quarter energizes in 2033, after posting $75 million of collateral and signing for 14 years. The same 50 MW in Houston posts no rule-mandated security, signs no minimum-take contract, and can be live in…

The 2% Funnel: 474 GW Requested, 9 GW Approved, 5.8 GW Energized in ERCOT
Governor Abbott's August 3, 2026 letter to the PUCT and ERCOT put the number at "approximately 474 gigawatts of requests to connect to the Texas grid," more than five times ERCOT's 85,508 MW peak record, about 90% of it data centers. ERCOT's own status table…

A Factory Owner's Guide to the PJM Capacity Charge
A 5 MW plant in Met-Ed territory will pay about $568,000 for capacity in the PJM delivery year that starts June 1, 2026. In the year that started June 1, 2024 the same plant, with the same load, paid about $50,000. Nothing on the plant floor changed. The RTO…

The $60 Million Deposit: How Equipment Slots Became Datacenter Currency
One GE Vernova 7HA.02 is 384 MW. At the ~$790/kW that BNP Paribas estimates GE Vernova is now getting for a heavy-duty turbine (July 2026), that one machine is ~$300 million of equipment, and the 20% reservation payment that holds a production slot for it is…

Behind the Meter, In Front of the Queue: 90 GW Announced, 2 GW Running
Datacenter developers have announced about 90 GW of behind-the-meter generation across 59 US projects, and about 2 GW of it runs, which is 2.2%. Another 1.2% is under construction, 36% holds an air permit, and 60% exists as a press release. The same month…

Recips vs Turbines vs Fuel Cells for a 100 MW Bridge
A 100 MW bridge plant run for five years costs $96 per MWh on solid oxide fuel cells, $104 on gas reciprocating engines and $112 on aeroderivative gas turbines. That is at 85% utilization with gas delivered at $3.78/MMBtu, and the ranking holds at every gas…

The 2 MW Plant Service Upgrade Nobody Budgets Right
A 400-person plant adding 2 MW of service pays for five things the switchgear quote never mentions, and together they run $400k to $1.2M with one month of bridge power. The calendar is worse than the money: run the project the way most plants run it, utility…

1872, Foundational Industries and Hadrian: Three Blueprints for the Autonomous American Factory
Three companies are building the autonomous American factory from three directions, and between July 2025 and August 2026 they raised $1.41 billion to do it. 1872 took $15 million to run robotic steel fabrication out of a 1903 building in Cincinnati.…

What Hyperscaler Nuclear PPAs Tell a Factory Negotiating a 15-Year Contract
Microsoft is paying about $112 per MWh for 835 MW from a reactor that shut in 2019, and it signed for 20 years. That is the Jefferies estimate for the Crane restart, published five days after the deal, and Bloomberg Intelligence put it at $100 (Bloomberg,…

Datacenter Construction Is Eating Your Electricians
Loudoun County's electrical contractors had 5,615 people on payroll in 2019. In the fourth quarter of 2025 they had 13,352, and by March 2026 14,022, a 138% increase in six years. That is what a few gigawatts of datacenter construction does to one trade in…

The 30% Fuel-Cell ITC Is the Last Federal Subsidy for On-Site Power
On July 4, 2025, Congress cut the federal investment credit for every kind of on-site generation a factory can buy except one. Wind and solar lose it unless construction starts by July 4, 2026. Gas engines and turbines never had it. Natural-gas fuel cells,…

Introducing the Large-Load Cost Table: 15 Markets Side by Side
Fifteen utilities, eight tariff cells each, and 45 of the 120 cells have no published number. That is the honest headline of the Open Factory Large-Load Cost Table, which launches as version 0.1: for a 50 MW connection in fifteen US markets, the study fee,…